For
these boreholes the tender of William Mathews, Brookside Works, Moston Lane,
Manchester, (at Widnes from 1926) of about £5,000 was accepted in November 1925.
Work on the site started in February 1926. Tenders were also received from E.
Timmins of Runcorn Cheshire, who subsequently sank boreholes at Creswell Pumping
Station, and from Le Grand, Sutcliffe.Boring Rig over Second Well The
steam-powered rotary boring rig used with the foreman Mr. Baker in attendance is
pictured. The site notes show that the hole took from October 1926 until January
1927 to complete to a depth of 550 feet below the bottom of the well. The first
borehole to be drilled by Mathews was the second for the Ashton Frost engine’s
well and after rapid progress between February and May 1926 boring stopped
because there was no coal available due to the miners’ strike. When boring
recommenced in August 1926 number two borehole was completed to 533 feet below
the bottom of the well within a month. Number four borehole, 530 feet below the
well bottom, was started in February 1927 but due to several breakages of
equipment and consequent recovery of pieces from the borehole the contract was
not completed until April 1929.
Tenders for the second engine and pumps, third boiler and
other equipment were invited late in 1925 and the specification made it clear
that the equipment was to be as similar to the existing as possible. The
contract was awarded to Hathorn Davey and Co. Ltd, Leeds, on 12th January 1926
in the sum of £11,230.
The miners’ strike also delayed the construction of the
second engine which was not erected at the Leeds works until May 1927.
In August 1927 the engine was delivered to Mill Meece by
rail to Standon Bridge Station, on the L.M.S. railway, one mile away from the
pumping station and then by road. It was then erected on site by Mr. H.V.
Cusworth, Chief Erector at Hathorn Davey.
In October 1926 the tender of Thomas Godwin for the
construction of the purifier house (Weir pump room) and third boiler seating was
accepted in the sum of £908. The boiler and other equipment was supplied and
fitted by Hathorn Davey and include the provision of Weir boiler feed pumps in
the purifier house to replace the engine driven feed pump and steam powered
injector supplied for the two on boilers.
The new engine and other equipment started working on 5th
May 1928, official duty test were carried out in September 1928.